Abstract: Project management is the art of matching a project’s goals, tasks, and resources to accomplish a goal as needed. We say “as needed” because one has limited time, money, and resources (human and machinery) with which to accomplish a goal. One can think of a project as a process. Preliminary investigation examines project feasibility. A feasibility study is the analysis of a problem to determine if it can be solved effectively. The results determine whether the solution should be implemented or not. Planning provides a road map for the software development process. It is probably the most time-consuming project management Activity. It is a continuous activity from initial concept through to system delivery. Plans must be regularly revised as new information becomes available. Schedule is a vital project management attribute in a market driven economy where time to market is critical to success. It takes an important role in the project planning activity. Individual projects are likely to differ considerably but following some classic project life cycle models. And the planning is pointless unless the execution of plan is monitored. Keywords: Project, Management, Feasibility, Planning, Scheduling Title: Software Project Management – A Successive Process That Bring a New System Author: JOYDEEP KUNDU International Journal of Computer Science and Information Technology Research ISSN 2348-1196 (print), ISSN 2348-120X (online) Research Publish Journals

________ is a critical path scheduling technique used for controlling resources.

What's on your critical path? Important tasks? Sure. Really important tasks? Of course. But is that all there is to it?  After all, every project task is important in some sense.  Within any project, the critical path is more than just a series of important tasks - it's a means for scheduling and management that relies on connections and consequences as a basis for planning project tasks and timelines.

As a project management technique, critical path analysis provides value in four (4) key respects:

  1. The critical path analysis is a means to estimate overall project duration.
  2. The critical path analysis is a basis to create a logical sequence of project tasks.
  3. The critical path analysis is a means to track project progress and identify delays.
  4. The critical path analysis is a basis to identify potential "fast-tracking" possibilities.

Practical Steps for Critical Path Creation

Critical path tasks are not considered "critical" on the basis of value or visibility, but on the basis of dependencies, which determine the overall length of the project. Since critical path tasks are connected tasks, a delay in one, can lead to a delay in all. As such, once identified, the critical path shows you what how to get your project done on time. 

Read more:  Project Scheduling Strategies

Critical path analysis relies on a few simple assumptions, as listed below:

  • Assumption #1 - Projects are made up of tasks.
  • Assumption #2 - Tasks are combined to form a timeline.
  • Assumption #3 - Within this timeline, tasks are either concurrent (can occur simultaneously) or sequential (one task cannot begin until the predecessor [superior task] is complete).
  • Assumption #4 - Sequential, dependent tasks make up the critical path.

Finding Your "Critical Path"

Critical path analysis begins with a task list, identifying all the key tasks required to complete the project at hand. This task list can be broken down into the following seven (7) key elements:

  • Tasks: Specific work activities.
  • Predecessors: Tasks that must be completed before any subsequent, dependent task can begin.
  • Durations: Task time estimates (from start to completion).
  • Early Start Time: The earliest point in the schedule at which a task can begin.
  • Early Finish Time: The earliest point in the schedule at which a task can finish.
  • Latest Start Time: The latest point in the schedule at which a task can start without causing a delay.
  • Latest Finish Time: The latest point in the schedule at which a task can finish without causing a delay.

From a practical standpoint, critical path analysis is all about creating "breathing room", to identify the tasks that must start and end at a specific point in time, versus those tasks which offer scheduling flexibility. Any worthwhile project management software will calculate critical path for you based on the tasks, dates and dependencies entered, but the logic behind these calculations should not be a total mystery, for it is the human element that must respond to project issues and changes on a daily basis - in real time.

Read more:  Project Management Checkpoints and Fundamentals of the Work Breakdown Structure.

Critical path analysis looks for the earliest and latest points at which tasks can begin and end. The calculation of earliest start times (EST) and earliest finish time (EFT) is used to create the project schedule. The calculation of latest start times (LST) and latest finish times (LFT) is used for schedule management, delay resolution, and fast-track planning.


Learn to Fast Track

When it comes to managing, you need more than one approach to be consistently successful. The way you manage when surrounding conditions are good, is not the way you manage when time is running short, resources are stretched thin and people aren't working together. That's what fast tracking is for - and we can teach you how it's done. Learn More


Calculations: Early Starts and Finishes

EST of tasks with no predecessors = First logical starting point.

EST of tasks with predecessors = Predecessor EFT (Earliest Finish Time).

EFT of tasks with no predecessors = Estimated task duration.

EFT of tasks with predecessors = (Task EST + Estimated task duration).

On the other side of the coin, latest start (LST) and latest finished times (LFT) are backwards calculations, considering the earliest starting point of the first subsequent task, minus the expected duration of the task under calculation. To calculate LST and LFT, you will start with the latest finish time and work backwards to calculate the latest possible start time.

Calculations: Late Starts and Finishes

Step 1 - Finding the LFT (latest finish time):

Considering the estimated "earliest start time" of any subsequent dependencies, what is the latest finish time for this task?

Task LFT = EST of the first dependent task.(Example: LFT of Task 1 = EST of Task 3)

Step 2 - Finding the LST (latest start time):

Considering the identified "latest finish time", what is the latest starting time for this task?

Task LST = (LFT – Task duration).

Example: LST of Task 1 = (Task 1 LFT - Task 1 Duration).


CHECK OUT THE FAST TRACK PROJECT TOOLKIT.

If you're looking for a fast, easy way to achieve project planning success, you'll find it inside the Fast Track Project Toolkit. This unique, informative online course gives you everything you need to become a project leader and fast tracking expert. Here's what you'll learn:

  • How to plan and govern projects using strategic project fast tracking.

  • How to use strategic project fast tracking to save time and make the most of available resources.

  • How to use strategic fast tracking to overcome project constraints and limitations.

  • How to use strategic fast tracking to negotiate with stakeholders and build shared expectations.

  • How to use strategic fast tracking to become a more productive project manager and team member.

Source: Unless noted otherwise, all content is created by and/or for ITtoolkit.com

What is a critical path scheduling technique used for controlling resources?

The critical path method (CPM) is a technique where you identify tasks that are necessary for project completion and determine scheduling flexibilities. A critical path in project management is the longest sequence of activities that must be finished on time in order for the entire project to be complete.

What is critical path scheduling?

The critical path method in construction is a method of project scheduling that breaks down required activities using a diagram to calculate the duration required to complete each activity. The critical path method, or CPM for short, is sometimes referred to as critical path scheduling.

What is critical path method example?

The CPM would describe the sequence that takes the most time. For example, if you're building a house, you would have several task sequences as follows: Each task takes a different amount of time and resources. It takes more time to build walls and lay the roof than to install faucets and fixtures.

What is the critical path in project management?

The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.